» News
Periodic Maintenance of Bahrain International Airport Runway
2017-11-09 - 3:49 am
Bahrain Mirror: Bahrain Airport Company (BAC) said that it has conducted periodic maintenance of the Bahrain International Airport runway during October to ensure the highest levels of safety and efficiency during aircraft landing and takeoff.
The company explained that the maintenance work took place over a period of 16 nights, and took a total of 48 hours of work by 185 employees, who worked for 3 hours a night on average using 70 vehicles on site.
Read More
- 2024-07-10Bahraini Authorities Summon Head of Sanabis Ma'tam, Threaten "Actions" Due to Mourners' Chants Against Israeli Occupation
- 2024-07-10Political Prisoner Mohammad Al-Raml's Family Say He's Vomiting Blood Due to Poor Conditions, Fear for His Life
- 2024-07-09Ali Al-Majed Arrested After His Return to Bahrain
- 2024-07-08Yusuf Al-Muhafdha: Convicted Returnees to Bahrain Have the Right to a Lawyer, Retrial, and Legal Guarantees
- 2024-07-08Reciter Mahdi Sahwan: Head of Manama Police Informed Me of Ban on Reciters Traveling to Commemorate Ashura